Eastside Elevated Water Reservoir

Share Eastside Elevated Water Reservoir on Facebook Share Eastside Elevated Water Reservoir on X (formerly Twitter) Share Eastside Elevated Water Reservoir on Linkedin Email Eastside Elevated Water Reservoir link
Elevated water reservoir with dark blue body and the text 'RIDGEFIELD' in orange.

The Eastside Elevated Water Reservoir project will construct a new elevated water storage tank on the east side of Interstate 5 in Ridgefield.

*Current project image is a conceptual rendering.

Scroll down to view the latest project update.

Purpose and Need

This project is critical to addressing the short- and long-term water supply needs of the eastern half of the City. The new Eastside Elevated Water Reservoir will have a capacity of approximately 2.5 million gallons (MG) that is expected to provide water supply for current and future demand for at least the next 15-20 years. A site plan is being developed to plan for a second water tank in the long-term future. When complete, the project will provide additional storage for current and future water demands and stabilize water pressure in a reliable, efficient manner.

The reservoir also provides an opportunity for public art to be displayed on the elevated tower. The process for this opportunity will be refined through the design stage.

Project Details

The project includes planning, modeling, design, construction and construction management phase services associated with the proposed Elevated Water Reservoir and connections to the existing water system in S. 5th Street.

Demolition of the existing structure was completed in February 2026 and a ceremonial groundbreaking was held on June 1, 2026. Scroll down to view the latest project update.

Construction began in July 2026 and is anticipated to be complete in June 2028. Scroll down to view the latest project update.

The Eastside Elevated Water Reservoir project will construct a new elevated water storage tank on the east side of Interstate 5 in Ridgefield.

*Current project image is a conceptual rendering.

Scroll down to view the latest project update.

Purpose and Need

This project is critical to addressing the short- and long-term water supply needs of the eastern half of the City. The new Eastside Elevated Water Reservoir will have a capacity of approximately 2.5 million gallons (MG) that is expected to provide water supply for current and future demand for at least the next 15-20 years. A site plan is being developed to plan for a second water tank in the long-term future. When complete, the project will provide additional storage for current and future water demands and stabilize water pressure in a reliable, efficient manner.

The reservoir also provides an opportunity for public art to be displayed on the elevated tower. The process for this opportunity will be refined through the design stage.

Project Details

The project includes planning, modeling, design, construction and construction management phase services associated with the proposed Elevated Water Reservoir and connections to the existing water system in S. 5th Street.

Demolition of the existing structure was completed in February 2026 and a ceremonial groundbreaking was held on June 1, 2026. Scroll down to view the latest project update.

Construction began in July 2026 and is anticipated to be complete in June 2028. Scroll down to view the latest project update.

  • September 2026 Project Update - Eastside Elevated Water Reservoir

    Share September 2026 Project Update - Eastside Elevated Water Reservoir on Facebook Share September 2026 Project Update - Eastside Elevated Water Reservoir on X (formerly Twitter) Share September 2026 Project Update - Eastside Elevated Water Reservoir on Linkedin Email September 2026 Project Update - Eastside Elevated Water Reservoir link

    Work is underway on the City’s new 2.5-million-gallon elevated water reservoir on the east side of Ridgefield.

    Since construction began in July, crews with contractor T. Bailey and its subcontractors have been busy preparing the site for the new reservoir. Work so far has included removing existing structures, clearing trees and vegetation, grading the site and installing erosion and sediment control measures.

    Two images of the prepared site with caption 'The site has been prepared by removing existing structures, clearing trees and vegetation, grading, and installing erosion and sediment control. The next phase of construction is primarily underground.'

    Currently, work is focused on building the foundation that will support the reservoir.

    Crews are installing 72 foundation piles, each about 24 inches wide. The piles will extend more than 90 feet below the ground to reach a strong layer of soil and rock that can support the weight of the elevated reservoir.

    While much of this work happens below ground and may not be easy to see from outside the construction site, it is an important part of building a reservoir that will safely serve the Ridgefield community for many years.


    Two images from construction of the piles with caption 'Crews installing foundation piles. The foundation of the reservoir will consist of 72 piles, extending 90+ feet below the surface. A cap will cover and connect the piles, providing a foundation capable of supporting the significant loads of the structure.'

    What’s Next?

    Once the piles are installed, crews will build the pile cap, a large foundation footing that will connect the piles below and support the reservoir above. Work on the pile cap is expected to begin by the end of October.

    The Eastside Elevated Water Reservoir project remains on schedule and within approved budget.

    Progress updates will continue as this project moves through construction phases. Thank you for your patience as this important investment in Ridgefield’s water system takes shape.

    Work is underway on the City’s new 2.5-million-gallon elevated water reservoir on the east side of Ridgefield.

    Since construction began in July, crews with contractor T. Bailey and its subcontractors have been busy preparing the site for the new reservoir. Work so far has included removing existing structures, clearing trees and vegetation, grading the site and installing erosion and sediment control measures.

    Two images of the prepared site with caption 'The site has been prepared by removing existing structures, clearing trees and vegetation, grading, and installing erosion and sediment control. The next phase of construction is primarily underground.'

    Currently, work is focused on building the foundation that will support the reservoir.

    Crews are installing 72 foundation piles, each about 24 inches wide. The piles will extend more than 90 feet below the ground to reach a strong layer of soil and rock that can support the weight of the elevated reservoir.

    While much of this work happens below ground and may not be easy to see from outside the construction site, it is an important part of building a reservoir that will safely serve the Ridgefield community for many years.


    Two images from construction of the piles with caption 'Crews installing foundation piles. The foundation of the reservoir will consist of 72 piles, extending 90+ feet below the surface. A cap will cover and connect the piles, providing a foundation capable of supporting the significant loads of the structure.'

    What’s Next?

    Once the piles are installed, crews will build the pile cap, a large foundation footing that will connect the piles below and support the reservoir above. Work on the pile cap is expected to begin by the end of October.

    The Eastside Elevated Water Reservoir project remains on schedule and within approved budget.

    Progress updates will continue as this project moves through construction phases. Thank you for your patience as this important investment in Ridgefield’s water system takes shape.