Share RORC Fieldhouse on FacebookShare RORC Fieldhouse on TwitterShare RORC Fieldhouse on LinkedinEmail RORC Fieldhouse link
The City is installing a Fieldhouse at the Ridgefield Outdoor Recreation Complex (RORC). The new structure will cover the existing batting cages adjacent to Fields 4 and 5 and add an Umpire Changing Room/Office.
This project is funded by a Washington State Legislature Capital Budget Grant and is being completed in coordination with the Ridgefield School District and Ridgefield Raptors.
The addition of a metal building around the batting cages will allow them to be used year-round. Additionally, an Umpire Office and Storage Room will be added to the end of the existing batting cages. The structure will include power for lights and outlets as well as ventilation.
We are currently reviewing plans submitted by the contractor and working on acquiring the necessary permits. Construction is expected to begin in February 2025 and be complete in April 2025.
The City is installing a Fieldhouse at the Ridgefield Outdoor Recreation Complex (RORC). The new structure will cover the existing batting cages adjacent to Fields 4 and 5 and add an Umpire Changing Room/Office.
This project is funded by a Washington State Legislature Capital Budget Grant and is being completed in coordination with the Ridgefield School District and Ridgefield Raptors.
The addition of a metal building around the batting cages will allow them to be used year-round. Additionally, an Umpire Office and Storage Room will be added to the end of the existing batting cages. The structure will include power for lights and outlets as well as ventilation.
We are currently reviewing plans submitted by the contractor and working on acquiring the necessary permits. Construction is expected to begin in February 2025 and be complete in April 2025.
In 2023, the City received a WA State Capital Grant for improvements to RORC and has worked with the Ridgefield Raptors to identify items for which to use the grant funds.
Fieldhouse Concept Approved - 2024
RORC Fieldhouse has finished this stage
In early 2024, the City, Raptors and School District reviewed and approved concept plans for the Fieldhouse.
Bid Awarded to Contractor - July 2024
RORC Fieldhouse has finished this stage
Review of Plans and Permit Acquisition - February 2025
RORC Fieldhouse is currently at this stage
Begin Construction - Late February 2025
this is an upcoming stage for RORC Fieldhouse
Tentative schedule dependent on permits and weather.
Complete Construction - April 2025
this is an upcoming stage for RORC Fieldhouse
Tentative schedule dependent on permits and weather.